"We need to understand what we want to do: we will probably not restore all the equipment because not everything was new, not everything was upgraded, and we will need to build a new one. This is our opportunity to modernize the power system faster than we planned in Last year, "Sakharuk said. According to him, instead of a substation in the territory of 50 ha "you can build contact distribution devices based on new technologies" that will occupy much less territory.
"This is a 100 m building that replaces the entire large substation. It is more expensive in terms of construction, but it is more reliable and durable, it is automatic inclusion, exception, it is a completely different level of automation and a completely different level of reliability," - explained the executive director DTEK. He also noted that the complete restoration of all the destroyed objects will need "one year to two, and maybe even more.
Všetky práva vyhradené IN-Ukraine.info - 2022